Core application “IEnsure” run from DR Site has been successfully tested without any flaws

DR SITE Management:

We have updated and fully tested the Disaster Recovery processes which are set in motion when a disaster strikes. The VPS (virtual private server) which is installed and managed at the data center of Silver lining located at geographically dispersed site Bhairahawa, Rupendehi district is now fully functional.

The system has been executed to backup automatically all incremental database files From the Main data center at the Head office to the DR center.

Also, the IT department is performing back up of all new application deployment files at the DR center.

RTO (Recovery Time Objective):

Test time elapse from the moment of the disaster till the business functions again have been successfully accomplished within less than 30 min.